Construction Activity for July 25 - Aug. 6


The following is a schedule of construction activity at Hunter Hall (222 East 16th Street) from July 25 through August 6, 2016. Please feel free to contact us at projects@friendsseminary.org or call our Information Line at 646-979-5225 for questions or comments. WORK HOURS

  • Monday through Friday: 7am – 6pm

  • Saturday: 9am – 3pm

  • No work on Sundays throughout construction (except in an emergency)

As weather conditions and unforeseen circumstances may influence the progress of the work, all dates and times mentioned may be subject to change.

INTERIOR WORK

  • Build-out and reconstruction of interiors.

  • Continued installation of mechanical, electrical, and plumbing (MEP) services.

EXTERIOR WORK

  • Structural steel reinforcement at the East side stair bulkhead.

  • Welding of steel studs on the metal deck for new fifth and sixth floors. This requires a diesel generator for the welding process and can be noisy. Tishman will complete this work as expeditiously as possible to reduce the temporary impact on neighbors.


  • Installation of hoist on north facade which will be used for transporting workers and materials to upper levels of the project site.

  • Installation of bricks and concrete masonry units (CMUs) on both north and south facades.


  • Waterproofing and fireproofing at columns, and final enclosing of exterior columns.